Lekaj shows why 63m euros should be given to the Pristina highway- Skopje

Minister of Infrastructure, Pal Lekaj has clarified in the Parliament why the Kosovo government has allocated 63m euros to the company “Bechtel Enka”, concerning the Pristina- Hani-Elez highway. Lekaj has clarified in the Assembly that the outcome of this part was meant to be completed in January 2018, but forced to postpone [...]
Lekaj has clarified in the Assembly that the outcome of this part was meant to be completed in January 2018 but forced to postpone it until December 31, 2018.
He has said that delays due to neglect by the past government have prompted the work for which the company has demanded compensation to postpone, broadcast news.net.
He has said that for three years the government has made no payments.
“Works would have to be completed in January 2018, but have not occurred because of delays from the previous government and we have been forced to postpone it December 31st 2018. If you go to Arbitrage the entire budget could go to”, Lekay said.