Memorial Misuses, Stealing From the Blood of martyrs

The National Audition Office in Kosovo has made public its findings in public institutions. Of the findings of this office at the Memorial Management Agency, a mismanagement in project planning has been noted, with this result reflecting on the creation of additional costs. From the findings of the audience, [...]
Of the findings of this office at the Memorial Management Agency, a mismanagement in project planning has been noted, with this result reflecting on the creation of additional costs.
From Auditor's findings, it is known that in this agency, for projects at the UCK's Memorial complex in Penushe, for the Memorial Consort of Raqak, for the April Memorial complex 27th, in Gjakova, for the Memorial Concert of the NLA Witnesses, in Mary, and for the National Witness Association in the Vreleve were additional contracts of 170 thousand euros.
This had happened as a result of shortcomings that have poorly analysed projects and designs for building complexes. Additional jobs have been argued by the contract manager and allowed by law, yet it is noted that there has been a frequent phenomenon, and it is being repeated over the years”, released by the Auditor's Office, writes the news.
As it becomes known, additional jobs have been reasoned by the contract manager and allowed by law, however, it is noted that there has been a frequent phenomenon, and it has been repeated over the years.
According to the ZKA, poor project planning results in the need for changes in projects, and this reflects directly on the creation of additional costs. As a result, these additional jobs endanger the funds allocated for other projects by unable to finance new projects.
In this case, the Auditor's Office has recommended to the Director General must ensure that all planned projects are well drafted and detailed. Under this recommendation, this would avoid starting quality projects and avoid additional jobs.