The municipality sépo can now bring to Pristina 21 new buses

Filled out were the buses of the “Urban Traffic”, during the two days of traffic ban in the capital's central area, as a measure for improving air quality. After government subsidies, this company offered free transportation to citizens on its three lines, with 30 new buses coming to the capital [...]
After government subsidies, this company offered free transportation to citizens on its three lines, with 30 new buses in the capital last year.
Even so, 21 buses of this company are staying in the company's parking lot. I VACO in Czechia, KTV reports.
For this, the head of the public municipal company “Rubiku Urban”, Halil Mustafa says they are not paying rent. While adding that delays in the renovation of the garage are the main cause of their failure.
This, since the EBRD has conditioned the arrival of buses with the renovation of the garage.
And completion of the works, which started a year ago, could take another few months after the Pristina Community has cut off its operator contract. NN Pristina.
Despite some demands, television has never been allowed to shoot inside the garage since the garage renovation started.
The only time the media have been allowed to enter it over the past 13 months is a Shpend Ahmeti rally during the campaign.
In the punished company, they say they've done almost all the work.
Contacted by television, manager of NN Pristina, Ademi Berisha, has left the municipality, which, according to him, has delayed the contract for additional jobs.
But in the municipality they say the punishment has come precisely because of the job.
According to Tahiri, these delays, although harmful, do not endanger the project and the loan for bus purchase.
In December 2016, the Pristina municipality had signed its initial contract with “NN P RlSTINA” for the renovation of the Urban Traffic Object, worth 1m euros of most money, has been granted by the EBRD.
While on June 21, 2017, she had earmarked 166 thousand euros for the second contract, for performing additional jobs.
Works initiated more than 400 days ago, according to the initial contract, have had to be completed in 60 days, while those of the additional contract within 30 days.