13 years from beginning works in Pristina-Mitrovica magistrate, angry citizens

Since 2009, work had been under way for road construction that connects Pristina, Vushtrria and Mitrovica. However, the work has dragged on and has not yet been completed. Meanwhile, even in the areas that were arranged, there were collapses of asphalt. In January of last year, it was yet to be a year from [...]
Meanwhile, even in the areas that were arranged, there were collapses of asphalt. In January of last year, it was still one year without the asphalt of a part of the magistrates, and there were street collapses in the village of Mazzi. And since then, the road has remained in that condition.
The road had collapsed as a result of erosion near the road by a private company that had begun digging for an object.
The Ministry of Infrastructure in a written response to Kosova Prees has said that things have begun, but because of some shortcomings in this magistrate, they have been banned.
The economic operator has been contracted, jobs have begun, but shortcomings have been found in the project and without the elimination of these shortcomings, cannot be continued. We are awaiting the elimination of shortcomings in the project by relevant authorities in the MMPHI, including the designer, and immediately after the improvements made in the project, jobs will continue”, they have said.
Citizens say this road is high-risk, as there is the possibility of accidents.
Agim Ramadani has said that the disorder of this collapsed part is a major hostage to citizens. He stressed that the problem could be solved very quickly.
There's actually a big hostage that's causing us, we have to constantly go halfway down to get to this part. I don't know why this big procrastination for a very small problem that can be solved very easily”, he said.
Citizen Gafur Latifi said that as a result of this road disorder, there may be an accident, as it is a serious risk.
That's it, two or three years. It's riskiness, somebody else can come down there, because the highways from the highway, unfortunately there could be an accident because of this” road, Latif said.
While some other citizens are told that enlightenment is missing and traffic is created.
Whatever they did... Little is dancing that people are afraid they can fall even below”, Besart Krasniqi said.
There were also bridges on the bridge in Babmoc. In this regard, the Ministry of Infrastructure says they expect to begin at the end of April.
The economic operator is contracted, preparations are under way, and we expect the start of operations at the end of this month”, said the Ministry's response.
Because of the collapsed bridge, citizens are forced to travel more miles to the second exit in the village of Stanofc, but some also oppose these rules.
Baytula Mehmeti has indicated that they have no other choice, since it has not been regulated for a long time.
I don't have a tear or go back to Stanofc and get back here. That's two years ago, they haven't fixed it, so the rest of Mazgi. That's how the road is broken and they're not fixing it, which is why I don't know”, Mehmet said.
Another citizen wants the Government to take steps faster.
And you're making it very difficult. It's a disaster. I'm just saying, I'm going to take steps faster than it was 2 years ago than that, and this government has been doing it.
According to the Ministry of Infrastructure, works on this practice are scheduled to be completed this year.