COSTT's cadre for reductions: The plan has been 8 to 2, but if this plan does not suffice reductions.

The head of the COST public company, Kadri Kadriu, has provided details about the realisation of energy reductions that began since yesterday. He said COSTT had sent KED a programme which, according to him, started around 10 yesterday, saying that since it was the first day, the method of realisation [...]
He said COSTT has sent KED a programme that, according to him, started around 10 yesterday, saying that since it was the first day, the practice has not been simple.
“Regarding the realisation of the disables, we've sent to KEDS a programme that started around 10 yesterday and since it was day one, the method of implementation has not been simple because that programme has been distributed throughout Kosovo and at 11 o'clock has started reducing”, Kadriu said.
Kadriu said the plan was eight to two (eight hours of electricity, two without power), where he said they reduced 150. ME, but he added that if this plan is not enough, reductions will increase.
“Plani was eight by two, which means we've reduced 150. So if the need for reductions increases, this eight-by-two plan will not be enough, but we hope that we will not go to that degree and of course it may be even shorter program”, Kadriu said, Clankosova.tv reports.
While, in terms of lack of electricity in some parts of the country by more than two hours, Kadriu said the implementation of the programme makes the KED, but also lack, he said it could be linked to technical deterioration.
The reality of the program makes KED, we don't, because we don't have access to consumers, and the way they've distributed it to consumers they probably had to follow our program. But there may have been more frequent bans that she may be connected to technical decay.