The Pristina municipality shows that when the work is finished with the Little Cafries

It's been two months since the start of the work on “Hydar Dusi” and “Fehmi Agani” otherwise known as the path to “Vogla catet” in Pristina. Works on these two roads are continuing further, and they are expected to end very soon. So has the Pristina Community announced, which [...]
Works on these two roads are continuing further, and they are expected to end very soon.
So has the Pristina municipality, which in response has said that the next week the segment to the crossroads will be ready for asphalt.
The “today has started with gravel compression. During the next week, the segment to the crossroads will be ready for asphalt and then in the two lanes will be free for circulation”, their answer is said.
Otherwise, the municipality has stressed that today is the 41st day of work and that it has not yet become 60 days, just as it was envisioned in the contract.
In their view, despite the problems that have emerged during these works, they are headed for completion.
“Today is the 41st day of work. Despite the problems that have emerged during underground installations, jobs in this area are going well and are towards the end of”, municipal officials have said.
Otherwise, the “Fehmi Agani” and “Hajdar Dushi” have been blocked since March 27th to make arrangements for fecal and atmospheric channeling on these two roads. /indysonline/