It's been three weeks since Ferronic stopped production.

After a seven-month failure to produce, the feronic metallural giant in Drenas is now facing another problem. This factory has been halting production for three weeks. Indexline sources within this factory suggest that production has been halted for more than two weeks. That's because part of [...]
Indexline sources within this factory suggest that production has been halted for more than two weeks.
This is because some of the roof of the electric furnace, which is the main part of its production, has been damaged.
Although efforts are being made to repair the furnaces, this can take time and is not known when production will be possible because of the very high cost of repairing them, reports Indexline.
This source revealed that electricity is also the problem of starting production. That is because as of April 1st, this giant will undergo prices at the international electricity market.
Meanwhile, around 820 workers and about 200 contractors are pending the launch of production. They are currently only doing more repairs, but not production.
We remember that this factory in 2016 faced a seven - month grace crisis because of a lack of resources