“Block B2” willing to return to production

As warned during the day, “Block B2” of the Termocentral Plant “Kosovo B” is willing to return to output before the scheduled deadline, so KEK officials say. “We are currently conducting launch procedures and once the request is confirmed by KEDS/ KESCO and KOSST are in need and willing to accept [...]
As warned during the day, “Block B2” of the Termocentral Plant “Kosovo B” is willing to return to output before the scheduled deadline, so KEK officials say.
“We are currently conducting launch procedures and once the request is confirmed by KEDS/ KESCO and KOSST are willing to accept 250 MW/h electricity” said of Express, KEK spokesman Skender Bucolli.
According to him, thanks to a major mobilization and maximum engagement of corporate workers, all technical defects have been managed and the return to work of this bloc, which has 250 megawatt power plants.
The Kosovo Energy Corporation, according to the production plan, has the capacity to produce up to 750 megawa hours of electricity. The “Kosovo A” and “Kosovo B” are currently available to produce electricity with 100 %s of capacity”
As far as supply is concerned, the current consumption is above the level of production capacities Kosovo is responsible for are other licensed operators in the market.
Essentially exclusive responsibility for supply of citizens with electricity under Z license RRE has KEDS/ EC SCO as a public supplier, which has to manage energy available from the country and abroad and not leave consumers without energy.