KEK reports A3 thermal power unit Kosova A has returned to office after sanim

KEK through a media report has announced that the Kosovo A3 thermal power utility Kosova A has returned to office this morning, as for a period it had been inactive. “The A-3 agency of the Kosova A thermal power plant, which was offline in the late hours of 2505.2025 due to the reaction of electrical protections [...]
“Nation A-3 of the Trmocentrals Kosova A, which was shut down in the late hours of 2505.2025 due to the T-3A transformatation response, has been successfully backed this morning. At around 0900, the unit was synchronized with the network and its current state was stable”, said the announcement.
“Thanks to the professional commitment of the TC staff, the Electricity and ZRRC Department, respectively, has been successfully completed, cleaning up insulaters and other necessary technical tests, which have enabled the A-3 unit to be restored to function.
Currently, KEK has two Kosova A thermal power units in operation (A-3 and A-5) and the B-1 plant unit Kosova B, with a daily capacity of around 10,500 TH”, KEK has announced. /Periscope/