Scandal at Food Agency: The 8 million-euro factory ends up at the operator that registered five days after the tender's announcement.

The animal waste processing plant, which has cost Kosovo over 8m euros -- which has not worked a day -- has been given for suspicious use to an economic operator. Millions of assets, surveillance equipment, trucks, property and machinery were given to an economic company only five days after the Food Agency and [...]
From Blerta Agushi
The next Periscope brings you the details of this scandal...
On September 18, 2024, the Food and Veterinary Agency, Operating under the Ministry of Agriculture umbrella announced public calls for the handover of the plant for processing animal waste that taxpayers have cost over 8m euros.
In a scandalous manner, just 5 days later, on September 23, 2024, the company that would later be announced winner of this tender is registered with the Doing Business Agency: KS & LIP S.P.K. IT.

A subx0> company formed”, with capital of just 10,000 euros and only 5 employees, was chosen to manage a million-euro investment.
That's not all.
From the findings and documents he provided Periscope, Turns out the main owners of the consortium are Naser Maloku and the Italian company, LOPIALIA 2000 S. P. A, each with 40% shares, while the third company is ARCHES BAU20% share.

The total capital of two major shareholders is only 8 thousand euros.

While Company AR CHES BAU It was registered just a month before the tender was announced on August 8, 2024, and its main activity is building residential objects, which have nothing to do with the processing of animal waste.
Meanwhile, the company LOPIALIA 2000 S. P. A It does not figure registered in Kosovo, at least according to research at the ARBK, which casts serious doubts about the winners of this project.
Periscop contacted one of his owners Naser Maloku to ask him about this contract they won, but he answered briefly: “Ani go over there you all have”
The tender won with light speed, questionable criteria and hiding agreement
The Food and Veterinary Agency has published the web site for all economic operators on September 18, 2024, but the winning name has not been published. This agency has not used the same transparency criteria with the winner, keeping him from opinion.
Periscopi learns from sources within the Ministry of Agriculture that the contract is deliberately being kept hidden by the media and the public, raising doubts about favouring an economic operator that was registered in the ARBK, five days after public announcement was issued.
Despite the public contract, it is not found on the Agency's website or the Ministry of Agriculture.
It is not even known how many years this factory, which has cost the country over 8 million euros, has been exploited.
Specifications say the start will be the day of signing the contract “and will end depending on the years appointed during the negotiations between the OE and the AK”.
A proclamation that requires an operator who has worked in this direction, but one of the shareholders is a construction company, contradicting the public criteria that the Food Agency has announced.
Thirteen-15m euros are required to have circulation in a fiscal year for the winner in the respective field, but it is founded only 5 days after the public call was announced.
By This is an executed Microsoft Office Doctore, powered by Office."On October 2nd, 2024 closes the deadline for accepting bids, and the meeting for opening tenders will not be public.
With this transparency concluded the public call, to be given in the exploitation of a Kosovo asset that has cost more than 8m euros and has been given to an economic operator registered at ARBK, five days after the state announced the tender. /Periscope/