Confirming KEK: A-5 unit in Thermo power plant Kosovo A BAR is out of place

Kosovo's Energy Corporation has indicated that the A5 block has again had stops, which spokesman Skender Bucolli has named as planned and necessary, since this entity was still in the testing phase. The A5 unit, which has now probably become the most recognised bloc in Kosovo, has not yet returned [...]
The A5 unit, which has now probably become the most recognised bloc in Kosovo, has not yet returned to full operation.
KEK spokesman Skender Bucolli, in a response to Gazeta Express, has indicated that since May 6th, after the phase of capital remont, the entity has been back in office and has been in the testing phase.
Kosovo's “Energy Corps reports that the A5 unit after capital remont has entered operation by date: 06.05.23 and has been in the testing phase.”, he said.
He added that during this period, some remarks have been recorded that are now in the phase of elimination. After this phase, the unit will be back in operation.
“Over this period all remarks that we are in the elimination phase are recorded and the unit is expected to return to operation soon. Furthermore, after capital remonts are planned-needed stops for eliminating remarks for safe operation of the relevant unit”, it concluded.