Rama progress does not trust the government, prepares for winter with 300 thousand euros for generator

The Pristina municipality, which is led by Progress Rama, has realised that this winter there will be reductions of electricity, so it has decided that a large amount of the money to go to spend on the purchase of generators, writes Periscopi. Most municipal institutions are equipped with generators, but in some of the educational institutions [...]
Most municipal institutions are equipped with generators, but in some of the educational institutions, they have been absent, and some have collapsed. Just 300 thousand euros is the amount of money the KP has seen buying generators, through tender procedures.
“Powering and assembly of generators for educational and educational institutions and other municipal needs”. So it's called the mayoral call, which he expects to finalize during October.

19 generators will be purchased with the power of the 26kW minimum engine.
11 powered engine 64.90 kW with reserve capacity up to 210 L
4 powered engine 64.90 kW with the reserve capacity up to 200 L.
Two with the 240 engine power here, 300 kWA.
Forty pieces of batteries - 100 ampers.
20 batteries - 200 amps.
So there are a total of 36 acres working in oil. The buyer will do their assembly.