The opening of the Pristina-Han of Elez still does not have a precise time when it will be ready for circulation, despite information that the same will be released within a month. Except for the risk of slipping a part of a hill, the same danger lies in a part of the road and [...]
The opening of the Pristina-Han of Elez still does not have a precise time when it will be ready for circulation, despite information that the same will be released within a month.
Except for the risk of slipping a part of a hill, the same danger lies in a broken section of the road, reports KTV.
The date will only be known when experts give you their appreciation.
Lekaj has said that they have taken on all the damage that can be done to other roads used by drivers, especially those of heavy vehicles.
To help find a faster solution has been offered to the highway construction company “Arba Xhaferi”.
We want to understand more about how the work is going, while the second part will focus on some proposals. We're actually supporting road closure, and then we're going to give new instructions with our team. As soon as the road is opened, this will enable safe movement for all and thus no longer will be dangerous”, said Riyadh Alkhazrai, director of the highway project.
The same day, the longest bridge on the “Arba Xhaferi” highway, which will be 5,7 km, and where some 300 workers are engaged.
The same is expected to end in September, three months before the completion of the entire highway.
While the ministry has pledged that it will no longer be indebted to the construction company.