New National Stadium, 1m euros for the lighting system (Photo)

It has been working for the new national facility for months. In the capital, there is currently only one stadium ready for international matches, while the “National Arena” is almost 55% of the total volume. Albanian Football Federation Executive Committee member brings to “Panorama Sport” details about the performance situation in [...]
Albania's Football Federation Executive Committee member brings to “Panorama Sport” details of the situation in the most modern national football facility to be built.
In his speech, it shows that about 13% of the investment was conducted and about 55% of the entire building's volume. I think it's toward the final stage of closing the ground floor.

It is now expected to begin everything for the construction and establishment of metal ladders in the stadium's tributaries so that they can get ready for concrete.
When we talk about performance, it may seem that a little has been done for anyone, but I can say that thousands of tons of concrete have been dropped and thousands of tons of iron has been spread.
Basically, 60,000 meters/cub concrete and about 7,000 tons of iron. I'm confident we're within all deadlines and in 2018 the stadium will be ready-to-be, says Dervisaj first.
HELPING
The person responsible for the stadium infrastructure in the FSHF Executive Committee provides data on the new lighting system that will be used in the new national facility. During his speech, Dervisaj brings details of what lighting will be like in the stadium and how much it will cost.

We've decided to replace it. It won't be the lighting that we used in Elbasan or Shkodra, but we chose the LED system. At cost, the assembly is slightly more expensive than the traditional system, but over time, it justifies costs in some respects. First, in energy savings, these lamps consume less energy. Second, light problem eliminated after a blink out-
PUNTS
The lamps are lit up immediately, while the traditional system requires a long minute to make the lighting of a certain section, then it must be expected to reach the temperature of the bulbs in order to be completely lit.
Finally, it's about a system that's based on the latest recommendations from U. FIFA EFA. Much to remember, Juventus was built in the new stadium with traditional lighting systems and then replaced with LED. The estimated preliminary cost for the lighting facility amounts to about 1m euros”, Dervisaj has declared.

Special Text System
The football national has held international matches in the face of a champion team like Spain in “Loro Borici”, but Dervisaj finds out about “Panorama Sport” that the new facility will have an even more special field than in Shkodra.
There was no need to choose a field with a heating system, because even the experts we consulted did not suggest, for themselves that there is no frost in our country.

However, we wanted it to be a field of maximum quality. It's going to be even better than the one in Shkodra. We didn't have any complaints from Spain, but for
We're going to look for perfection at this point”, followed by the EC member at FSHF.
Dervisaj further explains the special system that will be used for the grass. “As far as field is concerned, there will be system with ultraviolet lamps for grass only. Not only that, but in winter there will be a special cover, as long as the stadium stays closed. Along with all necessary deposits, approximately the area can cost 350 thousand euros. We will also use a method that takes place in nearly all large stadiums abroad.
On the side of the field, outside the game line, the best - quality artificial weed is placed. This, since it is not a part used to play, as we talk about several inches off the field line but is used to perform team training and heat, is the passage of side referees throughout the match, which often brings grass damage to that line”, has explained Arben Dervisaj to <1>Panorama Sport”.
Fasada / Start production, assemble after... 1 year.
Dervisaj, during his talk about the newspaper, also explains the fact that the facility has done much of the work, which at the moment still seems little to the eyes of observers. As detail, he recalls the fact that the facade is ordered and will begin to produce, but the assembly will take place much later.
There's also a specific one in the stadium building, which we'll start seeing since next week. Early on, the production of the facade, which requires its time, is expected to begin. We will not see it until it is mounted, but the fact that production is done in the air gives us time, as it will be ready after about a year, requires only assembly time later. So it is with many other things that have been ordered or tendered by the company, and at the plant we'll see only at the moment of the” assembly, Dervisaj explained.