Here is when the Pristina-Veternik road will be launched

It has been more than six months since work began on the road connecting Pristina with Veternik. This road from four lanes as far as it was concerned, with its expansion being eight lanes. Although works on this road were meant to last no more than 150 days, even [...]
Although works on this road were meant to last no more than 150 days, even though this deadline has passed, they are still continuing.
Days ago Minister of Infrastructure, Pal Lekaj was on the inspection of this road, to see the work for the nearest.
Meanwhile, in a proposal for Indexline, Minister Lekaj has said that there are still problems with expropriation and payment problems.
According to him, very soon work dynamics will increase, and by the end of November and early month of December the left-hand side of the Veternik road will be circulated.
“We've been on inspection in those opening workshops ions in Veternik and the dynamics of the jobs have led us to believe that by the end of this month one will be completed, but as we've later understood there have been and continue to have some problems with regard to expropriation and the lack of means of payment, and so for now we are committed to solving the problem and then will increase the dynamics of things that are possible by the beginning of November of December to be the left-hand side of the Vetnik road, the minister said.
Works on the road connecting Pristina and Veternik began in April. This road is one of Pristina's main roads.