For two years he placed no brick at Ferizaj Hospital

The brutal construction for Ferizaj's new Regional Hospital has been conducted during 2018/2019. It was the COVIED-19 pandemic, the change of governments and the interruption of the contract with the company that had the project suspended for two years. According to the Health Ministry, co-operation with the company has been disconnected because the same has made mistakes in the project [...]
It was the COVIED-19 pandemic, the change of governments and the interruption of the contract with the company that had the project suspended for two years.
According to the Health Ministry, co-operation with the company has been disconnected because the same has made mistakes to the object project.
This institution is now co-operating with the University of Pristina's Faculty of Construction.
The Dean of this faculty, Florim Grejchev, has announced by telephone that during this week they will be on the ground to report on the current state of the work.
He said they have signed memorandums of co-operation with the ministry we left last week, from which they have no financial gain.
And from the Ferizaj municipality, Deputy Chairman Lulzim Aliu, claims that if a company from this town had been contracted the works would already have been completed.
Meanwhile, the hospital currently exploited has small capacities compared to demands.
According to the director, Isa Berisha, this hospital covers the entire region, including the Kacanan municipality, the Hani of Elez, Shtrpce, Shtrpca, Shtrpce, a part of the Lipjan municipality and a part of the municipality of the Year.
According to the director, Isa Berisha, this hospital covers the entire region, including the Kacanan municipality, the Hani of Elez, Shtrpce, Shtrpca, Shtrpce, a part of the Lipjan municipality and a part of the municipality of the Year.