MP PDK: Tonight at midnight this KEK block comes out of operation

The energy situation in the country is just getting worse. After the A-5 bloc, the Kosovo Energy Corporation appears to have run into problems even with the A-4 bloc. Democratic Party of Kosovo MP Ferat Shala has said this bloc is obliged to shut down at midnight, due to the flow of the furnace. According to [...]
Democratic Party of Kosovo MP Ferat Shala has said this bloc is obliged to shut down at midnight, due to the flow of the furnace.
According to him, energy losses with this bloc's grasp are 14 0 SEW/h.
Even after the remont in the A4 Block, the Kosova A thermal power plant. A4 block, after a month's remont, has started working on a 02/10-2022, and now after two weeks it's forced to shut down at 24:00, because of the dump. The energy losses are 140 over.”, Shala wrote.
By contrast, it has been achieved for three months now to find a responsible company to rehabilitate unit A-5, which has been launched in office for nearly 50 years, with power of 210MW.
This block is currently in operation. KEK's problems with this unit have revealed Deputy Prime Minister Besnik Bislimi.
According to Bislim, some companies have submitted the bids, but say they are irresponsible and inconsistent.
We've been having trouble finding a responsible company that rehabilitates A5s. No. Now there's a few offers coming up, we're in the treatment process. Most of them irresponsible, not serious, because there is simply little readiness of renomic companies to continue to renew old coal capacities. They're not applying because they've received instructions to go and deal with renewable energy, their capacities to deal with renewable energy. It's not working at all A5, that's the problem. Without renovation...” has declared Bislimi.
Procedure proceedings for the remont of this unit had begun in late August. In the then KEK's announcement, the company reportedly will soon be selected.
“For the A-5 unit are currently under way in procurement procedures for capital remont, and very soon the responsible economic operator for this activity is expected to be selected, said the report.
Another report on this block, no more.