Exclusive: After Periscop's report, the prosecution launches investigations into the Gjilan highway, where “launched” 379 000 euros.

Another problem seems to have come up with the Ministry of Environment and Spatial Planning with the law. The Special Prosecutor has launched investigations into corruption into another project that is being carried out by the Ministry of Environment, Spatial Planning and Infrastructure, which is headed by Minister Lieburn Aliu and Deputy Minister Hysen Durmishi. It's about one [...]
Another problem seems to have come up with the Ministry of Environment and Spatial Planning with the law.
The Special Prosecutor has launched investigations into corruption into another project that is being carried out by the Ministry of Environment, Spatial Planning and Infrastructure, which is headed by Minister Lieburn Aliu and Deputy Minister Hysen Durmishi.
It's a contract that's being carried out in road construction known as the “Autastrada of Gjilan”, of which Periscope reported.
Eight contracts are signed for the construction of the 22-kilometer road and are being worked in just as many segments.
In January of this year, Periscope has published an exclusive text under the heading “Doubt that with forged bills, 379 thousand euros were evaporated at the Ministry of Lieburn Aliut”.
Periscop has reported that in the past year, the Ministry of Infrastructure, allegedly made an effective payment on behalf of the company “2 AGroup”, in the name of several jobs performed on the Gjilan Highway Project.
It is alleged that the company has offered a forged bill, misleading the ministry for a value of 378, 951. 39 euros for repayment, even though it hasn't done any work, there's not even been any such work that needs to be done for what's known as cysitulation.
Periscop sources have learned that the prosecution has already launched an investigation into the case. Initially, economic crime police have received all bills paid for tears 4 from the Ministry of Infrastructure, and then the prosecution has hired some Pristina University experts to measure the ground.
It turns out that the faculty has appointed three professors- assistants: Premtin Thaqi, Fidan Salihu, and noble Judge Loshi.
Periscop contacted Thaci. He has stated that he cannot speak without the D.A.'s permission, for he believes the subject is in expertise.
“Seek access to the Prosecutor, if they allow you, I can talk about this matter”, he said briefly.
Periscope has asked the prosecution to know how far the investigation has gone, but until the publication of this article, no answers have been made.
What did Periscop report?
Through the beacons, Periscop learned that in the past year, the Ministry of Infrastructure has made an effective payment on behalf of the company “2 AGroup”, in the name of several jobs performed on the Gjilan Highway Project.
The company allegedly offered a forged bill misleading the Ministry for a value of 378, 951. 39 euros for ransom, if he would not do so. No workWhat is more, there's not even been any such work that needs to be done for what's known as cysitulation.
Seeing that the bill was also signed by her official, the contract manager, Nebi Luzha, The ministry paid for the company's contract.W.
Periscope has published the certificate, the bill, and what is known as the task for this payment, which is listed as ʹSituation XIII. )
The documents, which see a total of 379,000 euros, also speak of an inaccuracies and are seen in simple eyes that are irregular.
For example, the pre-breaking situation that was issued on the 2.12th. 2121 is worth 505, 998.66 euros.
As shown in the certificate, this one has not been given away for 15 percent worth of the advantage of 84, 499. 67 euros, as the certificate shows it is an empty address book (based on contract rules, the advantage of 15 %s has been issued to the company for the final total sum of the contract)
But according to the contract, each situation needs to be dropped by the 15 percent advance the ministry stops and the final payment becomes the draw.
Based on the form of those known as ésituation, a total amount of the latest situation on the 1905,2022 results in many of 6. 477.161.77 euros (over 6m euros) is less than the total of the previous session, worth 6, 535, 225 euros, which amounts to a margin of over 43 thousand euros.
In this case, these tools were to be returned to the Ministry, as had to be stopped and advanced. Over 84 thousand euros.
Unless these tools have been returned to the ministry, this institution has been illegally released money from the company. 378, 951.39 euros.
This amount was issued on behalf of the 13th session, for work done.
On the “Cerficat of payments” writes that jobs done by the 1905. 2022 is 7, 010, 493 euros, while in the situation form by 19th. 05. The 2022 jobs performed are 6, 477, 161.77 euros.
So, the amount of over 7m euros seems to have been put in place, because no estimates can produce it, and in certificates it would have to be 6.4m euros.
A spring made plain, Periscope has learned that this bill was allegedly forged by the contract manager and the top company, taking over. Pay for jobs that have not been carried out on the groundThey didn't even exist like that.
Company consortium, “2A Group” S. P.K. ; “Ex-Fis” ; “2T” in 2018 had won the project (lot4) For performing work on the Gjilan Highway.
(PROJECTI It's definitely called: “Building A7 Autoway. 1-Disnivel Crossing A6 A7.1 (Bannoll) And the White Land, the Crossing Division, A6 A7.1 ) Udekrychi “Bresalcs”- L=22.31 km)
The value of the contract was 8, 700, 127.36 euros.
The leading company that has won the contract “2A Group”, which has been submitted to the fictional session, owns Valon Ademi, a friend of the procurement manager, Nexhat Krasniqi.
The owner of the company “
And owner of “Ex-Fis” is Isa Muharremi, and this company under CEC forms finds that in The latest election campaign has supplied the Vetvendosje Movement with oil derivatives.
Likewise, Valon Ademi is the owner of the other support company “2T”.
Included in this relationship, they are allegedly procurement, finance and contract manager.
Regarding all the payments made in the tear contract 4, Periscopi had requested an answer from the ministry, but has not received an answer.



Prime Minister Says 70 percent of road jobs were performed
Last Friday, the prime minister, Albin Kurti, has published a status he illustrated with a video out of fear, saying:
In fact, it is being worked on eight tears, not just in three, as the prime minister has written. Likely, not remembering the prime minister's fourth tear has to do with the investigation's commitment.
On February 15th of this year, Periscope had drawn some of the segments on this road, and according to the situation on the ground, the prime minister's assessment that 70 per cent of the work on this highway has been performed.
An estimated half a million euros on the Gjilan Highway was built off standards
On January 29, 2023, Periscope reported that The Ministry of Infrastructure has dealt with one contractor who is tasked with paying nearly half a million euros, though asphalt has not been set up to contract on God 2 on the Gjilan Highway. This tear has been won by the company from Albania “Gjoka Construction” at a value of 5, 906, 293, 67 euros. But, as Periscop learned, in this segment the company from Albania never worked, but the one from Kosovo “Kag Aspholt”, which has signed contracts with the ministry at the same time for TI's tears for the project, worth 11.6m euros.
Based on the Public Procure Law provisions, the sale of 100 percent of jobs to another company is illegal. That basically conflicts with Operational Guide for Public Procurement Article 18.11.
While the quality of the work is highly suspicious even in the other tears, Periscope has learned that in tears 2, the ministry is in trouble. This is because the labor company has not laid the asphalt down as it has been mentioned in the contract for the road to be of eropic stone, but the same has been paved with limestone, which is of the lowest quality and is much cheaper on the market, while payment is expected to be taken for cropstones.
The highways in Kosovo, in addition, are all built with eropative stones.
Although on that road segment, the layer of asphalt has not been worked on the contract, the company had billed nearly half a million euros at the ministry to avenge its work.
Periscope had reported that the ministry had not paid him, since asphalt has not been paved according to the contract. (It is unknown if the payments are made afterwards).
For all of this, Periscopi had requested an answer, and the Ministry of Environment, Space Planning and Infrastructure, but this institution has not returned.
In 2018, 8 contracts, worth 88, 618, 511,95 euros, were entered. After several months, the ministry was beginning to contract on additional jobs. These types of contracts for additional jobs have been connected until a few months ago. The amount of contract annex is 7.2m euros and based on the public procurement site, except in tears 3, there are two contracts for all parts. (a thing contrary to this law).
Following ties of initial contracts, the Special Prosecutor had launched investigations into former MIS Secretary Betim Recica, and ministry officials -- Isa Berisha, Leonora Limani and Mirdi Emni.
The prosecution's investigation had resulted in the rise of the indictment under suspicion of corruption against the four officials, and the trial against them is already under way. /Mentor Buzhala - PERISCOP/