Cutting Kurt With O The time has passed since one year in Pristina's three 13 million schools.

Kosovo Prime Minister Albin Kurti has blocked over 200m euros in public institutions' capital. For 14 months, the OSHP Procuring Organization has been on board. This has left many infrastructure projects, services and supplies stuck. The victim of this situation is the construction plan of three schools too [...]
Kosovo Prime Minister Albin Kurti has blocked over 200m euros in public institutions' capital. For 14 months, the OSHP Procuring Organization has been on board. This has left many infrastructure projects, services and supplies stuck. The victim of this situation is the plan for building three very modern schools in Pristina, for which some 13m euros were earmarked...
Once in charge, Prime Minister Kurti twice cancelled the OSHP Board selection competition. One that was initiated by the preliminary government and the other was initiated by him. In any contest the people who compete did not like it. Now in the third competition again, they're tacticalizing with candidates, not one added one, causing extreme delays for their selection.
Due to lack of the board, three schools planned by the Pristina municipality, worth over 13m euros, have been blocked in the Procuration Research Organisation, because during the election of winners there have been complaints by other companies.
In order to get to the signing of the contract, this epilogue job I have to give O The spread, which is otherwise known as the “Tender Court”
In July 2020, the Procurement Office in the Pristina municipality had announced tenders worth 10m euros for the construction of three schools. In this tender besides building schools with Private Partnership - PPP is also involved in providing maintenance and services in the municipality.
It's about schools in Matt County, Veternik's Sophaly. Everything was planned to be done in co-operation with the IFC (World Bank) and for the first time in Kosovo with the PFI method. Schools have been designed by an Italian-Colombia company selected by the World Bank and learned to be among the most modern schools in Kosovo.
The municipality had accepted several offers, but only two companies and one group of companies were prequalified:
1,“KPS, bid 16.8m euros, 2. Group “ABC” & “Beni dona” & “beni Dona Plast” & “Olti Trasing”, with a bid 13. 5 million euros. 3. “Bau Holding”, at 16.4m euros.

O expert The EP has decided on the municipality
Considering having met the requirements and had the cheaper price, municipal procurement in April 2021 has recommended the group of companies “for contract. ABC” & “Beni dona” & “Beni Dona Plast” & “Olti Trasing”.
The company from Albania, which is known for the reward with contracts from the Ministry of Infrastructure “, had not been hired with this decision. Pe-Val-Ku” This company has immediately complained in the municipality after the outcome was declared, claiming that the group of winning companies have failed to meet certain criteria, mainly dealing with the currency of several certificates.
The Komuna procurement has reviewed their complaint and dismissed it as unfounded, leaving the decision in force.
Immediately, yes, in April 2021 the company has complained in the OSHP against the municipality's decision. This body, based on legislation in effect, has authorized its expert to review the alleged evidence, engaging the official, Muhamet Kurtisaj.
As he has found PeriscopeCurtis White compiled the report in 12 days and delivered the same report to the OSHP.
As seen in the 15-page report, the OSHP expert has confirmed some of the claims of the complaining company, but basically has decided to put the Pristina Community's decision into force, because, according to him, the findings have been of little nature, within the freest price the winner has offered, worth over 3 million euros.
So Kurtisaj finally decided to recommend the O Board. The time has come for the municipality's decision to sign the contract and reject the complaint.
Since one year, the expert's report has remained in the OSHP archives, because there has been no board to make a decision about this subject, therefore the municipality plan has been delayed for more than a year and the money has remained blocked.
The expert's decision:

The municipality has not given up the project
Random, O Board of Directors The EPS, when it makes its final decision to file a complaint, is based on its expert's decision, which in this case was pro-communal.
The new government of the Pristina municipality, which is led by Chairman for Progress Rama, is determined to survive this project.
Pristina Education Director Besiana Musmati told Periscope that they have not given up this project.
We'll continue with the projects. Determined economic operators, if they agree with the signed contract, will nevertheless continue with the relevant planning of building schools”, she said.
In recent months, there has been an upsurge in the prices of construction materials, and the bid for the project has been at lower prices. That's why municipal officials are afraid of it.
This process has turned into a more complex process, due to the price erection of building products”, they have said from the municipality.
Where Will Schools Be Built?
The three new schools aim to reduce the number of students in many other schools in the capital, as they will have a large capacity for admission. They will even be destined for primary, primary and high school students.
School in SOFALIA
This school has a capacity for 720 students at 5,656 m2. Etage P+2 (three floor levels). School. Neve. 3 R.C. The number of cycles 2 cycles (from 2 cycles/ parale for each educational level). No. students. Class 36 students. No. Class 20 for 2 shifts
School in “ -Zona West
There will be 6,726 M2. School. Neve. 3 R.C. Number of cycles 3 cycles/ parale (out of 3 cycles/ parale for each educational level). No. students. Class 36 students. No. Class 30 for 3 cycles/ parale on each level. A total of 1080 students, 1 change
School in “
There will be 5,062 M2. School. Neve. 3 R.C. The number of cycles 2 cycles/ parale (from 2 cycles/ parale for each educational level). No. Students. Class 36 students. No. Class 20 for 2 cycle/parle on each level. A total of 720 students, 1 transfer.
The idea is for the school structure to be open and ready to adapt to future demands, leaving the possibility for bias depending on the need. Each of the modules will be flexible for changes within the same location. / P ERISCOPI/