Corruption Act against 10 people: Who they are and what tender they're suspected of, Periscope brings details.

Kosovo's Special Prosecutor today has filed charges against 10 people suspected of misusing the official position among them, former Infrastructure Ministry Secretary Betim Recica, former procurement manager Valmira Blace and former deputy minister Muhamet Gashi. In the prosecution's announcement, it is said that the same “in co-ordination using the task [...]
In the prosecution's announcement, it is said that the same “of co-ordination using office and official authority, as well as, overcoming their legal competencies, deliberately acted contrary to the Procuration Law, the Law for Budget Breaks of 2019, the Law on Management Public Finance and responsibilities, as well as other legal and legal acts”.
The Special Prosecutor of the Republic of Kosovo (PSRK) has filed an indictment at the Constitutional Court in Pristina today, against ten (10) defendants with initials B.R. V.B. E.M. B.D. N.P. G.M. I.B. and M.G.
The Special Prosecutor reports that the high-ranking defendants in the quality of official persons, in co-ordination using office and official authority, as well as, overcoming their legal competencies, deliberately acted contrary to the Procuration Law, the Law for Budget Divisions of 2019, the Law for Management Public Finance and responsibilities, as well as other legal and legal acts.
With these actions, defendants B.R. V.B. Mr. J.A. E.M. B.D. N.P. G.M. I.B. and M.G. in co-ordination they have carried out criminal work, using official position or authority, sanctioned by Article 1414 paragraph 2, regarding 31 of the Republic of Kosovo's Penal Code.
Meanwhile, the defendant V.B. He is also charged with criminal activity for falsification of the official document, by Article 427 paragraphs 1 of the Penal Code of the Republic of Kosovo.
It turns out the indictment was filed by Special Attorney Dren Paca, and the people against whom the indictment was filed are:
Izedin Bytyqi, former secretary at the Ministry of Infrastructure, Muhamet Gashi, former Deputy Infrastructure Minister in the government Hoti, Betim Recica, former secretary at the Ministry of Infrastructure
Valmira Blace, former director of the Procuration Division at the Ministry of Infrastructure,
Zymer Abdullahu, former secretary at the Ministry of Infrastructure;
Jethmir Alaj, official of the Ministry of Infrastructure;
Blerim Dina, former head of Public Prosecutor's Research Organisation
Goran Bilankovic, former O Board member The EP?
Nuhi Balarizi, former OSHP board member.
Periscop has managed to learn that it's the tender “Reconstruction of the R115 Regional Road, the Prizren-Presillament” weighs 14. million and 493 thousand euros.
The tender had been initiated at the time when the AAK minister, namely Pal Lekaj, was signed after the fall of this government, which was subsequently led by LDK minister Arba Abashi.
How has the process come about?
Initially, in October 2019, the ministry had announced the winnings of the tender for the first piece “Company Eskavator” Spec & “Pro&Co Group” shpk & “Best Company” and for the second half “Papenburg & Adriani”.
After announcing the outcome by the evaluation commission, seven companies had complained to the contracting authority, claiming they were eliminated contrary to the LPP and the tender file requests, and claiming that companies recommended for the contract have not met the criteria, neither technical nor cheaper. Later, the ministry had formed the assessment commission for reviewing company claims. After reviewing complaints, the ministry had rejected all companies' complaints and had put its own decision on contracting. Later, companies complained in O The E.P. O panel The EPS had proven that the tender has not been assessed as a set of laws and recommended that the ministry turn it into re-evaluation again. The OSHP confirmed that for this procurement there is cheaper responsible offer, alluding to the company's bid “Salla” for tear 2, which was cheaper than the winning bid for 749,621.40 euros. But in reassession O The KPS ordered the return and the first part of the tender, as there were violations.
But after the review, the same companies had again been declared winners. Only two operators, the concession “, complained to the contracting authority. Sa-Saw & Groma Hold”, and “2A Group &2T”. Again, the ministry had formed an assessment commission to review the complaints. The 2A Group &2T” offer had again rejected him, dismissing him as irresponsible. While, for “bid Sa-Salah” had said that it was an extra-off offer charged with claims at the KCPP, and did not take into consideration.
These two companies again complained at O The E.P. This institution authorized its own expert on screening evidence. The expert compiled the report in which he recommended that the subject return to reassess, because according to him, the ministry had violated the law when it declared economic operators responsible, while the company's bid “Sachath” had considered it long-term. Periscope learns that the KCPP had given an answer to the issue, where it said the alleged complaint was charged with e-procurement within the legal deadline.
Despite this, the panel had decided to meet at the time when there were strict measures of pandemic, and on March 18th it had issued a decision recommending that it continue with signing the contract with the economic operators the ministry recommended.
This game had lasted for several months until the LDK had come to power.
Former Minister Lumir Abdixhiku had found the tender on the table, for which the former procurement manager Valmira Blace demanded that it be signed, since she had the green light from the OSHP. But, Abdixhiku had been reluctant to sign the contract, as there was a KCPP decision confirming the opposite of the OSHP. After the collapse of the LV qualifying The V-LDK, power belonged to the LDK in qualifying with the AAK and at the head of the ministry had come Arba Abashi. He only found the tender on the table for the signature. His signature was signed by his deputy, Muhamet Gashi, after Abrashi was in America.
Now according to the prosecution's indictment, the tender is seen as being illegally linked, as companies had not met the terms for the contract. The O Panel is also seen on charges The EPS has made illegal decisions when it gave the ministry the right to contract binding.
Mismanagement even in the implementation of the contract
To finalize a public contract in full should be passed on several steps, and each is likely to risk it, since there is a possibility of misappropriation if there is no rigorous surveillance. One of them is also Execute on the ground. Companies often abuse infrastructure construction by placing products on roads that are not contracted to the price of supply but much cheaper, or by not putting in any of the contracted products, which are then paid. This is because companies offer more cheap prices, only to manage a contract. Periscope in the past year has found that this is exactly what has happened in the implementation of this contract.
Periscop has reported that neither asphalt nor a shield wall were worked as the Ministry of Infrastructure and companies connected to the “Reconstruction of the R115 Regimental Road Segration.
Periscope had been on the field in the past year and had found that products that were being placed on that road were not the same as those that figure in the contract, even some positions were not even set.
So on the 309. 2020 two contracts have been signed for Prizren-Prevall street, which range the value of around 14.5m euros.
Part one of the contract - Lot 1 was given” Eskavator Company Shpk & Pro-C Group Speed & Best Company Sword. The value of the contract is 7, 849, 716.18 euros.
Lot 2 is connected to companies”K.N.P. US Papenburg & Adrian Company Shpk. The value of the contract is 6, 643, 867. 79 euros.
Within the two contracts is the precaution and folklore feature, where all the work will be performed, such as clearing the terrain, road construction, landwork, concrete walls, signaling, etc. There are about 80 positions that need to be worked and each has its own value. So for each article (possibly) the amount to be executed, the price per unit for m2 or m3, and the complete value of the article is set.In tear-1, where construction is being done, companies “Eskavator Company Shpk & Pro-C Group Speed & Best Company Speed, Periscope has recorded these found:
So, according to the pageant, in terms of position:
At the location “1.3.1 Germing of the III category and IV of road construction, loading and carrying to the remote storage point of 14km”. No digging has been done in road construction at all.
Then to “1.3. 2-The digging of the V-VII category, the construction of the loading and carrying road to the remote depot of 14km”. Even here no digging has been done in road construction as required.
More details about positions:
“1.4.2 , Forum, transport and extend the low layer of road stabilizer, fractiony >63.0m in the main axis according to situation and indirect profiles with layers of d,min=50cm by indirect profiles, including the compression with which the 25.0m to the extent of the density required according to standards and standards in force for this type of work (80 MN/m2%>> The amount contracted 7, 893.30 m3. The price for units of 10 euros per m2. Total 78, 933.00 euros.
“1.4.3 Suppliers, transports, stretchings, and compacting of the tampon 0 MN/m2 of the broken limestone stone 0-63m with the thickness of=25cm, including the vortex-bundling of 25t to the mass density required according to norms and standards in force for this type of work”. The amount contracted 19, 210.50 m3. The 10 euro unit award. Total value 192, 105, 00 euros.
“1.4.4 Suppliers, transports, stretchings, and compacting (10)100 MN/m2 of the broken limestone stone 0-31.5m of the thickness of=15cm, including the string with the vibrator cylinder 25t to the mass density required according to norms and standards in force for this type of work”. The amount contracted 11, 144.40 m3. The price for units 10 euros. Total value 111, 444.00 euros.
“1.4.6 supply and processing of the Bitaggregate layer BA 22 mm of thickness to=7cm, si and the use of similar asphalt reinforcers (500gr/1 tonnes of asphalt) . The amount of Ilog in dense state” The amount contracted 54, 058. 55 m2. The price for 7.50 euros units. Total of 405, 439. 13 euros.
None of these four positions, which are seen as having a very high price, not being implemented on the ground, but it was only the corrosion of existing asphalt, from which only the level of asphalt of 4cm thick (so it's only becoming position No. “1.4.7fronization, emulsion spray, monobion layer production (with corrupt material) AB 11S m with the thickness of=4cm, as well as the use of aditive asphalt compounds of Aramid fibers and polyolephins like FORTA FI) or other materials of the same composition and characteristics (500gr/1 tonnes of asphalt) with thickness of=4cm, spraying 0.5/km2 of the bitoggregut surface. The amount of Ilog in dense state”
The contracted amount of this position is 54,058.55 m2, where the entity's price is 5 euros, totaling 270, 292. 75 euros.
While, at the location “2.4.1 (the material supply and the construction of the support wall with the Neoloy geoloy (or similar). The position includes all necessary materials for completing the wall according to the details provided. The filler of the walls be with these specifics (Cohesion c=0.0, the volume weight KN/3 and= 300)”, not as much material as is required in parameters, but with lower quality, which you see in the picture.
Periscopi has learned that regarding the failure to realise these positions, ministry officials have also made a sea report, where the findings have ascertained their laboratory. /Periscopi - Mentor Buzhala/