KEDS Continues Networking Investments for More Qualative Services in Obilic City

In the Obilic municipality, a Western section extends over 170 homes, which thanks to KED investments already have new networks of both medium and low tension. This investment made by the company and implemented by its own workers will bring stable and sustainable supplies to [...]
In the Obilic municipality, a Western section extends over 170 homes, which thanks to KED investments already have new networks of both medium and low tension. This investment made by the company and implemented by its own workers will bring stable and sustainable supplies to consumers on this side.
In this part of Obilic, which extends to thermal power plant “Kosovo B”, 143 new pillars -- 650 conveyors -- some 10,000m cables -- are located, which will significantly improve the quality of electricity services.
The ECDS Operations System Director, Bujar Jupay, said such investments will enable the delivery of quality services to our consumers.
“Taking into account that KED has inherited an old power grid, immediate investment actions in substations for modernisation and digitalisation of the network for the only reason, for consumers to benefit more efficient and more efficient electricity services”, he said.
Such KEDs are continuing in Kosovo's neighbourhoods, villages and towns, placing more contemporary equipment and equipment of the latest word of technology.
KEDS consistently engages in the mission's fulfillment imposed ten years ago: Light all over Kosovo with the most modern infrastructure.