At midnight the A3 block stops, KEK provides electricity from Albania

The trouble with the thermal blocks of the Kosovo Energy Corporation - KEK, they're not stopping. Once a block gets back to work, there's another one. Warnings are for a difficult winter, writes Periscope. After the temporary stabilisation of energy, after midnight today, exactly at 24: 00 p.m., they will be removed from office and [...]
After the temporary stabilisation with energy supplies, after midnight today, exactly at 24:00, the A3 thermal power block “Kosova A” will be removed from office.
Stopping the A3 block work, as he learned PeriscopeIt's because of a leak.
Sources from KEK have indicated that the ban, though forced, is planned, after saying the amount of electricity from Albania has been provided.
This Block has a production barrel about 200 MWh of electricity, and after returning to work the previous days of the B1 block, production passed consumption requirement. Thus, demand for electricity will be less than the first few days.
On the other hand, it is taught that Albania's hydrocentrics are producing full capacity, following recent rainfall. /Periscopi/