KEK Builds Operations Security in Production Units

The Kosovo Energy Corporation announces the opinion that, based on the Vjetor Vitor Bilanti Elektro-Energy (BVEE), and with the aim of boosting the security of operations and stability of the generation units during the winter period, the B-2 power plant unit Kosova B has begun its regular annual revision (8 days) from today to 15th. 11. 2022. During this [...]
During this period, but according to the BWE, KEK will operate with A3=125 units MW/h, A4=12 5 MW/h and B1=25 0MW/h.
Also supplied by B1 unit, the Termocos will be supplied by about 45-50. MW/h thermal energy, depending on Thermocos' demand!