Nijazi Thaci: We have long announced all operations on clearing the thermal power plant.

On today's morning in Obilic, black smoke has been seen coming out of the Kosovo B thermal power plant chimney, which has worried citizens. KEK Director Nijazi Thaci has said this has happened because of the cleanup of the thermal power plant and that such a cleanup is mandatory. He said they were notified [...]
KEK Director Nijazi Thaci has said this has happened because of the cleanup of the thermal power plant and that such a cleanup is mandatory.
He said all the acters have been notified of this, which he has denied the chairman of Obilik Xhafer Gashi.
“We've announced all operations on cleaning the thermal power plant. I can also prove that we have notified the municipality, the commander of the Obilic police station, and the Ministry of Environment”.
It's not extraordinary, it happens after any capital repair. This smoke happens because of the cleaning of the A3 block jar, which for 4 months has been in remont and now, after the end of the remont and before the start of the job, has to be cleaned up which lasts for four days by about three hours a day. It's an impossible technological process to escape. The thermal power plant is also equipped with outdated”.
We have announced that after every change in the materials from cold to hot, black smoke may emerge. Every 5 years it is mandatory to become such a cleanup”.
News that inspectors from the Environment Ministry were released at the scene has denied Thaci.
I don't have any information that went out at the scene. We are public companies, operating for all citizens of Kosovo equal to”.
Thaci said that when the overhaul is planned, they have not known there will be elections, and accusations directed at the company leading it are being made to receive electoral favours.
He also promised that during this winter, he will have the best supply as they can.