Rating exhumed over delays in highway work to Skopje

The Ministry of Infrastructure has not yet ascertained whether there has been delays in performing works by “Bechtel& Enka” for Elez's Pristina-Eater Highway. Even though they had rejected the newspaper and civil society reporting that annexes-contrasceptions expect the work to be completed on June 1st, representatives of this ministry have said that this findings would take place [...]
Even though they had rejected reporting the newspaper and civil society that annexes-contrasceptions expect the work to be completed on June 1st, representatives of this ministry have said that this findings will take place after recapitalising the contract, writes today “Koha Ditore”.
The contract on Road 6 and the construction of the Pristina- haniil highway project of Elez was linked on July 1, 2014, between MI and “Bechtel&Enka”. Just 18 days after the government's formation on September 27, 2017, Minister Pal Lekaj had signed the contract's extension agreement, but leaving commercial issues unadvanced, respectively, the cost of extending the deadline for 347 days.
And in November 2017, “Bechtel& Enka” from 14.78m euros, which was seeking damages caused by delays, had raised that amount to 63m euros. While on September 5, 2018, Minister Paul Lekaj and “Bechtel&Enka” had signed the third annex of 53m euros, changing the total value of the contract from 608.3430 euros to 661.448,430 euros.