This is the agreement signed by Lutfi Zharku and Bechtel- Enka for the millions scandal (Dok)

The Ministry of Infrastructure at the time it was led by LDK Minister Lutfi Zharku, had signed an annex with Bechtel Enkan, under which it became clear that the amount of money of 14m euros could even increase. So according to this document, it was entitled to the Bechtel company Enka's [...]
So according to this document, it was granted to the company Bechtel Enka so that I could seek additional compensation.
This is determined in appendix 3 defined as: The length of time to complete the contract.
In this annex of the agreement, both sides agree with the good will” for payment of this amount, defined as 50 %s of the 14.939.408.67m euros.
This annex has entered into force since the signing day.
According to the same document that has provided the newspaper Blic 50 per cent (50%) of 14,939.408.67m euros (according to the contract expansion agreement) will be billed to the employer (government) in the same month that this additional contract will be signed.
The same document says it does not necessarily represent the contracting rights of contractors stemming from the duration of time, but nevertheless represents a amount which the contractor considers less than its real amount, and is accepted as the good will of the parties.
The paper has tried to contact former Infrastructure Minister Lutfi Zharku to learn more about this agreement, but the latter has not responded.
Additional documents from the Infrastructure Ministry deal with Bechtel Enkan
Add 3: Longitude for completion
11 months and 11 days of time for closing the final cost.
1.1 extension of meeting payment deadline
Fifty percent (50%) of 14,939.408.67m euros (according to the contract expansion agreement) will be billed to the employer (government) in the same month that the contract extension will be signed and paid for with which the contractor should be paid in line with the contract deadline.
The remaining 50 per cent of the ETO sum will be included in the employer in new installments within the cash bills for January 2018 to June 2018 and paid to contractors in line with the contract deadline
This does not necessarily represent the contractual rights of contractors stemming from the duration of time, but nevertheless represents a sum that the contractor considers less than its real amount and is accepted as good will and in pursuit of the project's successful execution to avoid suspicion.
This amount of atonement does not specify a reference for future contractor claims, which may arise and be contracted, and is entitled to the contract that will be made in line with the actual contract spending.
However, the blame for the loss of 53m euros is not being accepted by any Minister of Infrastructure.
The current Minister of Infrastructure, Pal Lekay has blamed the loss of 53 million at former Infrastructure Minister Lutfi Zharku. Because, according to Zharku, he was able to carry out financial obligations to Bechtel-Enka company while they were at lower value.
“The minister has had the chance not to give the famous 14 million a chance to do 63 (which after non-stop negotiations is down to 53 million, which will therefore be 45 because 18 % The indirect VAT will be returned to the state budget when it was in the country where I am today, it has taken nothing, and now at least has the right to say such things that I thought I missed an evental meeting with”, Paul Lekaj had declared days earlier.