AV ONET: Prizren municipality, major lawbreaker

AVONET NGO network expresses deep concern over state of governance Community of Prizren, where efficiency, accountability and accountability to citizens are lacking in this municipality, is also one of the municipalities that draft paramas contrary to the nature of jobs. AV ONET has monitored and researched some of the lighting projects like the <x0 project. Efficiency [...]
AVONET NGO network expresses deep concern over state of governance Community of Prizren, where efficiency, accountability and accountability to citizens are lacking in this municipality, is also one of the municipalities that draft paramas contrary to the nature of jobs.
AV ONET has monitored and researched some of the lighting projects as project “The efficiency of public lighting in Prizren municipality” with a procurement number 622-19-8744-2-1<18x2>, where Prizren's municipality has not respected the bidding file criteria and also during the analysis and research of the tender file has been encountered in some irregularities, such as the project and the design of the tender's parliament, where according to research. The AVONET tender has no existing project, and this increases suspicions of misuse of this contract.
During AV Research ONET has identified that there is a change in the advance of initiative and procurement office, and the project has also been entitled Efficiency Light, while in parase light for high electricity consumption. AV ONET research has identified that in urban areas, lightlights with 150 W capacity have been removed, for reasons of high cost, while in the advance of the tender file have been asked to set light until 240 W, comes the question of what efficiency is this?
While the Republic's National Audition Office Kosovo, has issued a find with the B6-lack of the executive project, which is: Article 20 points of the Public Procure Guide (UOPP) requires that technical specifications for the labour contract should include an executional project as a substantial part of itself. And the 13th point: contracting Australia is responsible for drafting the execution project and which should be mandatedly attached to technical specifications which are part of the tender file. No container Authority is allowed to issue tender documentation without attaching the project's detailed description.
In the “cabinet operation contract below the height of elementary school in Mosshnikovs of Prizren”, worth 107.945, the municipality had not drafted the executive project, but had initiated procurement procedures, preparing only parasage and paraloga. The reasons for not drafting the project were the neglect of relevant officials and the fact that procurement procedures are not delayed.
Developing procurement procedures without executive project increases the risk of implementing jobs without standard building criteria, delays in realisation, and poor quality.
AV ONET, he wants to Kosovo Police and Prizren Constitutional Prosecutors to Begin Investigations into Finders AV ONET and Report National Office The audit.